Podcast: Ireland’s new planning consent regime – Part 4 is live, what it means for your project

Matheson LLP, Irish Law Firm · Matheson In Focus - Ireland's New Planning Consent Regime (Part 1)

About this episode

Part 4 is live: what it means for your project

Part 4 of the Planning and Development Act 2024 has come into operation.

In part one of a dedicated two-part series, we’re looking at what that means for developers and the teams responsible for delivering projects. Which application route should you use? What happens to applications already in the system? How should you programme the process? And what flexibility will you have once permission is granted?

Matheson partners Ruadhán Kenny and Maeve Delargy guide you through the key changes in our special edition podcast.

Topics discussed

Part One - Part 4 is live: what it means for your project
  • The new planning framework and transition rules. The speakers explain how Part 4 reorganises the planning permission process and why developers must establish which rules apply to each project. Applications already lodged, existing permissions and projects still in preparation may be treated differently.
  • Application strategy and realistic timelines. Project teams should confirm the correct application route, identify mandatory pre-application consultations and allow for environmental assessments, further information and appeals. The speakers stress that statutory decision periods do not guarantee usable permission by a particular date, and missing a deadline does not mean automatic approval.
  • Making planning permission work for delivery. Developers should consider design flexibility, conditions, permission duration and phasing early. Later alterations and extensions are subject to statutory processes and limits, rather than a general right to redesign or obtain more time.

Episode extras

Page

Planning and Development Act Hub

Read More
Insight

The new mandatory EIA Scoping requirement: five key questions for renewable energy developers

Read More
Insight

Eolas Planning Report – delivering robust permitting

Read More
Insight

Irish Planning Legislation Overhauled – Yet To Be Implemented

Read More

Podcast Transcript

Read the full transcript — Ireland's new planning consent regime - Part 4 is live: what it means for your project
  • [00:00:01] John Davis (interviewer): This is Matheson in Focus, examining the legal issues shaping business in Ireland.
  • Welcome to the first of our two conversations about Ireland’s new planning rules. I’m John Davis, and today I’m joined by Ruadhán Kenny and Maeve Delargy, partners in Matheson’s Environmental and Planning Group. You’re both very welcome. Part four of the Planning and Development Act 2024 has come into operation. So today we’re looking at what that means for developers and project teams.
  • [00:00:35] John Davis (interviewer): Where do you apply? What happens if your application is already in the system? What should you allow for in the programme? And how much flexibility do you have once you get permission? In the next episode, we’ll get into the practical details of the regulations, forms, notices, environmental screening, and how to submit the documents. But today, we’re looking at the act itself and what it means for your planning strategy. Throughout the conversation, I’ll keep coming back to one question for our guests.
  • [00:01:06] John Davis (interviewer): What does the project team need to do differently, or at least check afresh? Maeve, let’s start with the big picture. What has actually come into force and why does it matter?
  • [00:01:18] Maeve Delargy: Part four is now in force. This is the part of the act dealing with development consent or planning permission. But it isn’t the only change today. The department’s notice also covers remaining provisions on what counts as development, environmental assessment, housing supply, enforcement, appeals and records, and the transition between the two acts. The supporting regulations come into force alongside them.
  • [00:01:41] Ruadhán Kenny: Yeah, it’s the milestone we’ve been waiting for. The act was signed in on the 17th of October, 2024. And I think people expected a big bang at that stage, but it’s come into force in stages. So what we need to distinguish is what changes today from what was already in place. I suppose the important thing is the whole system hasn’t changed overnight.
  • [00:02:00] John Davis (interviewer): So some of this is already up and running. Maeve, what changes had already taken effect?
  • [00:02:06] Maeve Delargy: So the development plan and new area-based plan provisions took effect on the 31st of December 2025. In other words, the rules for making plans were already in place before the new rules for applications. The commission had also been restructured and, as hard as it is for us all to remember, the name change today isn’t actually the first day that An Bord Pleanála became An Coimisiún Pleanála.
  • [00:02:27] Ruadhán Kenny: Yeah, I mean, the other one is everyone’s bugbear, the new judicial review procedure that started on 1st of August 2025. So that removed the leave stage under the new procedure. So that’s the separate step of asking the court for permission to bring the challenge. So that’s not new today either. And it’s important to establish which procedure applies to the decision or the process being challenged and how the transition rules affect it. The date someone brings a challenge obviously doesn’t settle that on its own.
  • [00:02:54] Maeve Delargy: And there are two other dates worth keeping in mind. Chapters 1 and 2 of Part 22, which cover the initial urban development zone framework and site identification, they both started on the 9th of June 2025. So today brings in the remaining UDZ provisions. And the housing strategy provisions in Chapter 1 of Part 7 started on the 31st of December 2025. So it’s just the remaining housing supply provisions that come in today and not the housing strategy framework starting from scratch.
  • [00:03:22] John Davis (interviewer): So how did those earlier changes fit with part four coming into force now?
  • [00:03:27] Ruadhán Kenny: Well, we have the new application process alongside the rules for making plans that were already in place that Maeve’s just mentioned. So for developers and the public, we’d encourage early involvement with relevant development plan, the area-based plan, any proposed variations, and any candidate UDZ process, rather than waiting until the application is ready. We’d also recommend checking which plans and transition rules apply to the site. Today’s commencement doesn’t automatically replace every existing plan. It provides the context for developing the development strategy.
  • [00:03:57] Maeve Delargy: Yeah, and that’s why today matters for this discussion. The new consent framework now applies to new applications subject to transition rules, which we’ll come to shortly. It takes us from the planning context through the application and permission to delivery. And one other point, the relevant framework is the 2024 Act as amended. So including the Planning and Development Amendment Act 2026, together with the applicable regulations. And our advice would be to work from the full framework rather than just assume that the original 24 text is the complete picture.
  • [00:04:29] John Davis (interviewer): And we’ve heard that word overhaul quite a lot. Maeve, does part four completely reinvent the application process or bring together what was already there?
  • [00:04:41] Maeve Delargy: Well, for part four, I’d say it brings the rules together and reorganises them with some important changes. It isn’t a complete reinvention. It puts standard applications, direct applications to the commission, alterations and extensions, and local authority and state authority development into a more coherent framework. The core principles are familiar. You still need a sound planning case, the relevant environmental assessment, and public participation.
  • [00:05:05] Ruadhán Kenny: Yeah, but that doesn’t mean that it’s just new section numbers. So there’s important changes to decision periods, what happens if they’re missed, to alterations and extensions, and to applying before specified design details are confirmed, so the flex. So the department’s aim is clearer routes and more certainty. And that matters to developers and funders, but obviously it isn’t a promise of approval or a guaranteed start date. And as we’ve said, the wider plan-making and JR reforms were already underway, and those are separate from the Part 4 changes.
  • [00:05:34] John Davis (interviewer): So the basic principles are familiar, but there are changes that matter. Ruadhán, how should a developer approach this?
  • [00:05:42] Ruadhán Kenny: So I think our advice would be to look beyond the application itself. This framework covers the route, the assessment, conditions, and appeal, and what happens after permission. It’s about the whole life of the permission, from early planning to construction and any changes along the way.
  • [00:05:58] Maeve Delargy: Yeah, and that’s particularly important if you’re buying a site or approving an investment. It’s not just can we get permission, it’s will that permission allow us to deliver the project as planned.
  • [00:06:08] Ruadhán Kenny: So we suggest looking at those four things together, the route, the duration you need, the phasing, and the flexibility. And ideally, that discussion will happen well before the application is almost finished. And it’s also worth remembering that the other consents and delivery issues don’t disappear just because the new act is in force.
  • [00:06:26] Maeve Delargy: You still need a sound planning case. The framework tells you how to bring it forward and how it’s decided.
  • [00:06:32] John Davis (interviewer): Okay, let’s talk about projects already in the system. Ruadhán, if a developer submitted an application before the 26th of November, do they have to start again?
  • [00:06:44] Ruadhán Kenny: The department’s notice says that applications lodged before midnight on the 25th of November continue under the 2000 Act. And section 626 preserves that act for applications made under Part 3 before the relevant appeal and for specified appeals brought before repeal. So existing permissions are a separate question. Section 188 treats specified permissions and approvals under the 2000 Act as a corresponding permission under the new act. So we’d start by looking at where the project actually stands. Do you have permission?
  • [00:07:15] Ruadhán Kenny: Are you waiting for a decision? Are you still preparing the application? For consultations, opinions and appeals, the step you’ve reached and the relevant saving provision matter. An early meeting doesn’t automatically keep every later step under the old rules. And for live projects, we recommend a short transition record for each one, the reference, the legal route, the key dates and the basis for the next step.
  • [00:07:38] John Davis (interviewer): Now let’s take a new application. Maeve, how do you work out where it should go?
  • [00:07:44] Maeve Delargy: Okay, so the Act distinguishes standard development, generally applied for to the planning authority under Chapter 3, from defined Chapter 4 development, which goes directly to An Coimisiún Pleanála, The categories in the Act and the consultation process determine whether the direct route is available. A project doesn’t go straight to the Commission just because it’s large, commercially important, or needs an early decision. The Commission’s pre-application process establishes whether Chapter 4 is the appropriate route. If it’s not, the Commission identifies the relevant route, if any.
  • [00:08:14] Maeve Delargy: We’d recommend settling that early before the project teams builds the application around an assumed route. It’s also helpful to map the associated infrastructure and other consents. You may need more than one decision and different authorities may deal with different parts of the project. For utilities and infrastructure, our advice would be to check the definitions and the specific statutory undertaker provisions rather than assume the route used last time is still the right one.
  • [00:08:39] Ruadhán Kenny: And we suggest putting that into a short planning consent strategy that the whole team can use. So who’s responsible for each application? What assumptions are being made about the programme?
  • [00:08:48] John Davis (interviewer): And Ruadhán, what about talking to the authority before you apply? When is that a legal requirement rather than just a useful conversation?
  • [00:08:58] Ruadhán Kenny: So for some specified developments, it’s a statutory requirement. So section 89 includes developments of at least 10 housing units, student accommodation of at least 200 bed spaces, and non-residential development of at least 1,000 square metres, as well as other prescribed categories. And then for large-scale resi development or LRD, there’s the separate LRD meeting and opinion process with the relevant zoning requirements and the opinion or qualifying certificate obtained within the preceding six months. So, we’d suggest using that discussion to test the difficult issues, infrastructure, access, phasing, environmental assessments, and any conflict with planning policy.
  • [00:09:35] Ruadhán Kenny: It can really help to involve the right technical people early. But I suppose just to give the caveat, an encouraging meeting isn’t a planning permission, as with under the 2000 act, these consultations and opinions don’t bind or prejudice the later decision under the 2024 Act.
  • [00:09:50] Maeve Delargy: Yeah, I mean, it helps you prepare, but it’s certainly not something the funding team should treat as a commitment to approve.
  • [00:09:56] John Davis (interviewer): So that brings us to timing. Maeve, how much confidence can a developer put in the new decision periods when setting funding and construction dates?
  • [00:10:04] Maeve Delargy: Well, the mandatory decision periods do matter, but they don’t give you a guaranteed date for permission that you can use. For standard applications, Section 101 starts with eight weeks from application where neither appropriate assessment nor environmental impact assessment or EIA is required. If either is required, it’s 12 weeks from the submission deadline. Further information process affect how those periods are calculated. And for commission appeals, Section 113 includes 18 weeks when neither assessment is required and 26 weeks where either is required. Again, there are qualifications.
  • [00:10:36] John Davis (interviewer): And if the deadline passes, do you get automatic approval?
  • [00:10:40] Maeve Delargy: No, you don’t. For the planning authority, the Act provides explanations, consent to more time and deemed refusal options. The Commission continues to decide an appeal with explanations for delay and reporting or payment consequences in the relevant circumstances. We therefore recommend having someone responsible for the correspondence about delay and extra time. It’s not just a matter of watching the calendar.
  • [00:11:02] Ruadhán Kenny: Yeah, and I suppose we’d suggest keeping those stages separate in the programme, the application decision, any appeal, the permission itself and the work to satisfy conditions. A base case and a downside case can be more useful to have than just one optimistic date.
  • [00:11:17] John Davis (interviewer): And what if the team is ready to apply, but a particular design or technology choice isn’t settled? Ruadhán, can the application still go in?
  • [00:11:27] Ruadhán Kenny: Yeah, very helpfully. The act has a controlled mechanism for that. It’s the flex opinion that was brought in in the latter stages of the 2000 act or very similar. So for standard development, sections 93 and 94 deal with specified aspects that are unlikely to be confirmed by application date. And then sections 118 and 119 provide the corresponding mechanism for direct applications permission. So what you do is you identify what isn’t settled, explain why it makes sense to apply now, and propose at least two approaches or a defined range.
  • [00:11:58] Ruadhán Kenny: The authority then considers whether the application can proceed on that basis. So, it’s not a general right to redesign later. You have to have clear limits on the uncertainty. And the permission restricts the choice to the approaches or range in the application and requires notification before your relevant development begins. So, obviously, as technical issues, we’d suggest discussing the flexibility that you need with your engineering and procurement teams. Is it the tech? Is it the dimensions? Is it a particular component? And can your environmental assessments cover those defined choices as well?
  • [00:12:29] Ruadhán Kenny: That’s a really important point.
  • [00:12:30] Maeve Delargy: Yeah, the decision maker and everyone else taking part need to understand exactly what’s being assessed.
  • [00:12:36] Ruadhán Kenny: Yeah, and I think in the next episode we’re going to look at the regulations, practical requirements for documenting that flex and notifying the final particulars.
  • [00:12:44] John Davis (interviewer): Maeve, what if the proposal conflicts with the development plan? Can the developer assume an appeal will sort that out?
  • [00:12:52] Maeve Delargy: Sections 99 and 110 set out different mechanisms for the Planning Authority and the Commission on Appeal. So the Planning Authority route involves a formal material contravention resolution, public participation and approval by at least three-quarters of the total membership. The Commission’s powers depend on specified grounds including strategic or national importance, conflicting or ambiguous plan objectives or consistency with specified higher level policy. And there’s also a separate provision for chapter four applications. The decision maker can’t just set that part of the plan aside.
  • [00:13:25] Maeve Delargy: There has to be a specific legal basis. And we’d recommend identifying the conflict and the statutory route early and would advise against basing an acquisition or funding decision on the assumption that an appeal will solve it. As we said earlier, the new plan-making provisions were already in force. And we’d recommend early planning policy review and engagement in relevant plan-making or variation processes alongside preparation of the planning application itself. Comparing the development plan, zoning, higher level policy and any potential controversy before the design and commercial strategy are fixed can help identify issues early.
  • [00:14:02] John Davis (interviewer): Okay, so let’s say the decision has arrived and it’s positive. Ruadhán, what should the team do next?
  • [00:14:09] Ruadhán Kenny: Well, obviously after popping your champagne, the first thing we think everyone should do is review the conditions with your delivery team. They’re not just extra pages at the back of the document. So Section 87 means there can be conditions covering infrastructure, security, sequencing, management, environmental protection, many other matters. And they need to be assessed along with the construction and the funding arrangements. So it can help at that stage to bring together the developer, the planning advisor, the engineers, the environmental team, the procurement and the funders.
  • [00:14:40] Ruadhán Kenny: And for each condition, we’d suggest asking who’s responsible for compliance, what evidence is needed to demonstrate compliance, and when must compliance be achieved? And then we’d also recommend considering how long the permission lasts. So Section 177 has a five-year default with a scope for a different period, generally between 2 and 10 years, and then longer periods for Chapter 4 development. And then for resi development of at least 10 units, Section 178 requires the application to specify the duration sought and include a phasing plan.
  • [00:15:10] Maeve Delargy: Our advice would be to make that case in the application rather than leave it until the permission is about to expire.
  • [00:15:16] Ruadhán Kenny: So matching the duration and the phasing to how the project is expected to be delivered and keeping the dates on the project dashboard.
  • [00:15:23] John Davis (interviewer): As we know, projects change along the way. So what can a developer do if the design needs to change after permission?
  • [00:15:32] Maeve Delargy: Yeah, they do change. But Chapter 5 provides a structured process for both alterations and extensions. And it distinguishes non-material from material requests. That’s really important with materiality, including environmental assessment triggers and other material changes. So a non-material alteration is dealt with differently from a material request, which can be granted, modified, conditioned or refused. And there’s also provision for consultation before making the request. A change can look small on a drawing, but it still needs careful assessment.
  • [00:16:04] Maeve Delargy: We’d recommend checking it against the permission and the statutory tests, including the environmental position. A clear comparison between what’s permitted and what’s proposed can help before any commitment to the change. For an extension, the request must be made before the expiry of the permission and development must have commenced. So extension of duration have further statutory conditions, including the restriction to one extension only under the new framework. The 2026 Amendment Act introduces an aggregate cap of twice the original duration, including the specified treatment of earlier extensions granted under the 2000 Act.
  • [00:16:40] Maeve Delargy: Those limits don’t mean you’re entitled to extra time. You still have to meet the other statutory conditions.
  • [00:16:45] Ruadhán Kenny: Yeah, and certain existing resi permissions have a separate qualifying alteration mechanism under Section 138A. So look, we’ll flag the practical processes in the next episode. But I mean, ultimately, it shouldn’t be mistaken for a general right to redesign.
  • [00:17:00] John Davis (interviewer): Ruadhán, if a project director takes three things away from this, what should they be?
  • [00:17:06] Ruadhán Kenny: So first, a review of your pipeline and the rules applying to each of your projects. Second, an updated planning consent strategy, so covering the route, your pre-application work, your assessments, your timing, and policy case. And then third, a review of how your permission, once you achieve it, supports delivery, the conditions, the flexibility, duration, phasing, and any changes that you might need.
  • [00:17:27] John Davis (interviewer): In the next episode, we’ll get into the regulations, what goes into the application, further information, electronic submissions, environmental screening, and practical steps for alterations and extensions. But for now, Ruadhán, Maeve, thank you so much. Join us next time for part two of our conversation about Ireland’s new planning rules. Thanks for listening to Matheson in Focus. As every development is different, we recommend that you take advice on the right approach for your project.
  • [00:18:01] John Davis (interviewer): You can find out more and get in touch with Maeve and Ruadhán through Matheson’s website, matheson.com.