The Planning and Development Act 2024 is now fully in force, although transitional rules continue to govern legacy cases.

A key element of the landmark act, referred to as Part 4 and its supporting regulations, came into effect on 26 November 2026 and govern how development consents are prepared, determined and implemented, subject to certain transitional rules for legacy cases. For developers, investors and public bodies, the task is to apply its requirements to applications, permissions and project delivery.

What has changed?

Part 4 consolidates, reorganises and clarifies categories of development consent procedures, moving requirements from regulations into primary legislation. It is not a wholesale reinvention of every planning process.

Its practical requirements must be read alongside the supporting regulations (which largely mirror the previous regulations), environmental assessment provisions and transitional rules.

These consent changes sit within the wider 2024 Act framework (as amended by the Planning and Development (Amendment) Act 2026), including plan-making, institutional and judicial review reforms introduced in earlier phases.

The practical significance can be summarised through five themes:

  • Preparation: confirm the consent route, consultation requirements and submission readiness.
  • Process: check eligibility, notices, validation, submissions and further information requirements.
  • Decisions: understand the applicable determination, conditions and appeal procedures.
  • Implementation: revocations, alterations, extensions of the duration of permissions.
  • Transition: identify the rules governing legacy applications, appeals and permissions rather than assuming every case follows the 2024 Act procedures.

Planning permission changes in Ireland: Part 4 of the Planning and Development Act 2024

Matheson in Focus podcast

Ireland’s new planning consent regime

Development consent changes: Part 4 and connected provisions in practice

Development consent routes and application requirements

Read More

Decisions, conditions and statutory timelines

Read More

Environmental assessment: connected Part 6 requirements

Read More

Pre-application consultation and large-scale residential development

Read More

Planning appeals: linked Part 12 procedures

Read More

Alterations, extensions and existing permissions

Read More

Enforcement: Part 11 compliance procedures

Read More

Land powers, compulsory acquisition and compensation

Read More

Strategic Development Zones and Urban Development Zones

Read More

Please note: this is general information, not project-specific legal advice.

Planning and Development Act 2024: frequently asked questions

Yes. Part 4 of the Planning and Development Act 2024 (the “2024 Act“) and the connected changes covered here are in force, alongside the supporting regulations.

The 2024 Act was commenced in stages, rather than on a single date.

Commencement does not mean that every existing application, appeal or permission has moved to the 2024 Act procedures: the applicable savings and transitional arrangements remain important. Establish the legislation governing the particular process before relying on a procedural requirement or deadline. Department commencement confirmation.

Yes. New planning applications submitted on or after 26 November 2026 are processed under the Planning and Development Act 2024 and its supporting regulations.

Applications, appeals and permissions originating under the Planning and Development Act 2000 require separate transitional analysis; commencement did not produce a universal switch of every live case to the new procedures.

The starting point is the project’s actual procedural and consent history. Department transition guidance.

Applications lodged before the 26 November 2026 changeover continue under the Planning and Development Act 2000 where preserved by the relevant transitional provisions. Applications lodged from that date are subject to the Planning and Development Act 2024 requirements, subject to the applicable savings.

Confirm the precise rule for the application or process concerned, especially where consultation, an appeal or a proposed alteration spans commencement. Use the forms, public notices and supporting documents required for that process; the passage of time does not itself transfer a legacy case to the new procedures.

Department transition guidance.

Separate arrangements apply to direct applications to An Coimisiún Pleanála (the “Commission“) where pre-application consultation began under the Planning and Development 2000 Act but the application had not been lodged before 26 November 2026.

The Commission’s guidance distinguishes completed consultations, which can support a Chapter 4 application for the development covered by the determination, from consultations still underway.

Commission Transition Guidance for Direct Applications.

Part 4 of the Planning and Development Act 2024 places application preparation and determination within a reorganised statutory framework.

Applicants should check eligibility, pre-application consultation, large-scale residential development requirements, public notices, supporting documents and validation. Submissions and further information also need attention.

The practical task is to identify the requirements for the relevant route, rather than assume every procedure is new or that updating the application form is sufficient.

Overview of consent procedures.

There is no single decision period for all applications and appeals.  For standard applications, the principal periods are eight weeks from application where neither appropriate assessment (“AA“) nor environmental impact assessment (“EIA“) is required, or 12 weeks from the submissions deadline where either assessment is required.

The Planning and Development Act 2024 sets different decision periods for cases before An Coimisiún Pleanála. These include a period for standard appeals where neither EIA nor AA  is required, a 26-week period where either assessment is required, and a 48-week period for strategic infrastructure applications.

A statutory determination period is not an overall delivery timetable and does not remove appeal or litigation risk. Confirm the operative legislative and regulatory provisions before including specific deadlines in a project programme.

Department explanation of statutory timelines.

Certain supporting provisions of Part 12 of the Planning and Development Act 2024 have been in force since June 2025, however as the new appeal procedures only apply to Part 4 consents, they have not been used to date.

The new appeals procedures will begin to take effect as Part 4 consent decisions are made by the authorities.  Appeals which were already commenced under section 37 of the Planning and Development Act 2000 (the “2000 Act“) will continue to be processed in accordance with the 2000 Act.

The practical issues to check include which procedures apply to the particular appeal, including any transitional saving for a legacy application.

Check who may appeal, what must be submitted, the information forming the appeal record and the applicable time limit. Prepare for potential appeal issues when compiling the original application.

Overview of appeal procedures; Department reform guidance.

Apply the provisions relevant to the project, including environmental assessment, enforcement, housing supply, heritage, land powers, compensation and development zones.

Specialist projects may also require attention to Dublin Airport or public authority powers. These requirements have their own procedures and transitional arrangements; they are not all contained in Part 4 of the Planning and Development Act 2024.

Judicial review and costs rules also remain relevant to challenge risk, although the wider litigation regime is a topic in its own right which we will address separately.

Department circular on judicial review costs already introduced.

An Coimisiún Pleanála’s guidance confirms that a permission granted under section 34 of the Planning and Development Act 2000 (the “2000 Act“) before 26 November 2026 is deemed by section 188(1) to be “a permission granted under section 98 of the 2024 Act”.

ACP Guidance – Advice notice on appeals under the Planning and Development Act dated 16 November 2026.

Permissions granted following appeals under section 37 of the 2000 Act are similarly recognised as permissions under section 109 of the 2024 Act.

Part 4 of the 2024 Act addresses alterations, extensions and duration, but the available route depends on the permission, proposed change and transitional rules. Section 180 deals with the effect of judicial review on permission duration and has been in force since 1 August 2025.

Do not assume that a permission gains extra time automatically or that every proposed redesign can use an alteration procedure. Conditions, implementation status and expiry dates should be reviewed when preparing project programmes.

ACP Transition Guidance for Direct Applications.

  1. Identify the legislation governing live applications, consultations, appeals and permissions, including cases preserved under transitional arrangements following the 26 November 2026 changeover.
  2. Check the relevant Part 4 route, eligibility, consultation requirements, forms, notices and supporting documents.
  3. Review permission conditions, duration and the correct route for any alteration or extension.
  4. Coordinate environmental assessment and any relevant land, housing supply, heritage or enforcement requirements with the Part 4 consent strategy.
  5. Keep programmes, due-diligence checklists and internal documents aligned with the operative requirements and applicable savings, retaining appropriate contingency.

Commencement and transition guidance

Latest Insights

18 min
26/11/2026Podcast

Podcast: Ireland’s new planning consent regime – Part 4 is live, what it means for your project

6 min
09/11/2026

The new mandatory EIA Scoping requirement: five key questions for renewable energy developers

2 min
29/10/2026

Eolas Planning Report – delivering robust permitting

10 min
27/07/2026

District heating in Ireland: a market at a turning point

3 min
10/03/2026

Urban Wastewater Treatment Directive – Irish transposition

3 min
10/03/2026

Environmental Omnibus update

Our Team

Maeve Delargy

Maeve

Delargy

Partner

Ruadhán  Kenny

Ruadhán

Kenny

Partner

Our Expertise

Environmental and Planning

© 2026 Matheson LLP | All Rights Reserved